A federal court late Monday lifted a hold on an Army plan to detonate degraded lead explosives at an ammunition plant in Iowa — clearing the way for an operation that has sparked contamination concerns across the state.
The ruling follows a tumultuous week of protests, lawsuits and delays, including a Monday missive from President Donald Trump stopping the operation until the court could consider a legal challenge brought by environmental groups. The president also suggested that the incoming governor, Rob Sand (D), should decide whether the operation goes forward — and that Sand would be held responsible for any negative consequences.
Army officials say the operation, which was planned for Wednesday before Trump intervened, is necessary to deal with a cache of hazardous lead azide — a component of munitions that becomes highly reactive when it deteriorates. The detonation has been delayed several times amid outcry from residents who say they were not given sufficient notice or input.
Many Iowans have questioned the timeline of decisions leading to the detonation plan, which has been in the works since at least March. Government records show the Army initially hired a Georgia firm to use a chemical treatment to neutralize the waste — an approach that would have produced less environmental fallout — but the contract was canceled after two months.
Even with measures to limit the spread of hazardous material, Army projections suggest the controlled explosion will unleash a plume of lead particles extending as far as 100 miles away. Lead is a potent neurotoxin for which there is no established safe level of exposure, according to the Environmental Protection Agency, and it can persist in ecosystems or in human bodies for years.
Army officials have insisted the detonation must happen as soon as possible to avoid an even more dangerous spontaneous explosion.
Before Trump’s order and then the latest court ruling, the Army was set to conduct the operation Wednesday, when it said weather would be optimal. In a filing over the weekend, the Justice Department invoked an emergency provision of federal environmental law, saying it allowed the Army to move forward with a controlled detonation despite a court-mandated pause and ongoing lawsuit.
In a post on Truth Social, Trump had said the operation should not move forward until a court could rule on a legal challenge from environmental groups — even though he agreed with an Army assessment that controlled detonation was the safest option.
He suggested giving Gov.-elect Rob Sand (D) final approval over whether the plan goes forward.
“If he or the Courts do not agree, we will have no choice but to not proceed with the controlled removal of these hazardous materials, and be forced to hold the incoming Governor responsible for any and all death or destruction caused by this very unfortunate, and longterm, situation,” Trump wrote.
Army representatives did not respond to inquiries earlier Monday about how they plan to proceed.
In a post on X, Sand said that the Trump administration “should make this decision based on the information they have from the people they brought in to do the job months ago.” He urged federal officials to share more information about how the situation came about.
In late March, records show, the Army hired MuniRem Environmental, a company that specializes in chemical disposal of hazardous waste, for “lead azide neutralization at Iowa Army Ammunition Plant.”
Valentine A. Nzengung, a University of Georgia geochemist and founder of MuniRem, told The Washington Post that his company’s approach would have stabilized the degrading explosives without unleashing contaminants into the surrounding environment, and for a much lower cost than the planned detonation. He said he has deployed the technology several times before, including at another munitions manufacturer that stored its lead azide in drums similar to those used at the Iowa plant.
But the MuniRem contract, which was first reported by the New York Times, was abruptly canceled in May. Nzengung said he was told that the Army decided to go with controlled detonation “out of an abundance of caution.”
Shortly afterward, Nzengung sent an email to EPA regulators urging them to consider the potential environmental effects of detonation.
“Such an event would constitute both an explosive incident and a hazardous-waste dispersal event rather than a complete destruction of contaminants,” he wrote.
He never received a reply.
Deteriorating lead azide at the Iowa facility has been a concern before — more than two decades ago.
A 2014 release describing the U.S. military’s efforts to develop greener explosives explained that the project was established 10 years earlier in response to worries about the stockpile at the Iowa Army Ammunition Plant.
The document came from the public affairs office at Picatinny Arsenal, a military research and manufacturing facility in New Jersey.
It is not clear whether the stockpile that was flagged in 2004 is the same as the one that was found to have become unstable this year, prompting the Army plan to dispose of it through open detonation. But the 2014 release, which described lead azide as highly sensitive and toxic, suggests that the Defense Department was concerned enough to fund a search for alternatives.
The Army did not immediately respond to inquiries about the canceled contract or the Defense Department’s past concerns about lead azide storage.
Most Iowans, including Gov. Kim Reynolds (R), did not become aware of the Army’s latest plan for the materials until Nov. 15, when the Army issued an advisory about a resulting plume of lead dust that could reach up to 100 miles away.
Mary Strausbaugh, a 68-year-old Burlington resident, questioned the move to leave any decisions to Sand.
“It’s just a little ridiculous that we’re making it political and not about the people and the property and the things that are more important,” said Strausbaugh, who said she has lived in the area her entire life. “We’re making it about politics, and now saying that the next governor needs to deal with it. … We can’t put this off till January. Why doesn’t Reynolds do something about it?”
Strausbaugh also wondered why information has been slow to trickle out since the initial delay.
“They stopped detonation on Friday so that they could get more information out there and tell people what’s going on and inform people better,” she said. “There’s not been anything like that. … There’s really nothing coming out, except you watch, you know, local TV news, and they’ve got maybe a little more information, but not a lot.”
It remains unclear exactly how the Army’s nearly 10,000-pound lead azide stockpile became so dangerously volatile.
According to a sworn declaration that Army Col. Aaron Teller, an explosives specialist, filed in response to the permit challenge, the substance was packed in 68 barrels filled with a mixture of water and ethanol and stored in concrete-lined underground magazines. American Ordnance, the military contractor that operates the munitions plant, inspected the barrels every September and added additional stabilizing fluid as needed, Teller said.
American Ordnance did not respond to a request for comment before publication of this article.
On March 12, local news reported, plant operations had been paused so experts could conduct a safety review of lead azide that required disposal. The MuniRem contract was issued two weeks later.
But Teller’s statement said that Army Explosive Ordnance Disposal inspected the magazines where the lead azide was stored on April 28. They found “unknown crystal growth” in 58 of the 68 barrels, much of it concentrated around the internal rim and underside of the lids. Crystallized lead azide is highly sensitive, and even the smallest movement or burst of static electricity can cause it to explode.
Because the barrels were no longer safe to open, American Ordnance did not refill them with stabilizing solution this September, Teller said, causing more liquid to evaporate and making the lead azide even more susceptible to spontaneous detonation.
Recent fluctuating temperatures have increased the risk further, he said.
“The real choice … is not between a detonation and no detonation. It is between a planned and mitigated detonation and an unplanned and unmitigated explosion,” Principal Deputy Assistant Attorney General Adam Gustafson wrote in a court filing accompanying Teller’s statement.
The Army has said it plans to cover the lead azide magazines in two stories’ worth of sand, which it will then spray with misters to limit the amount of lead that is released in the explosion. In an assessment released Wednesday, the Army concluded these measures will ensure the operation has a “less-than-significant” impact on the environment and public health.
Apart from his concern about the environmental effects of detonation, Nzengung of MuniRem said the Army’s account raised questions about how the lead azide was stored.
If the barrels were inspected every year, he said, something drastic — such as a leak — would be required to change the fluid levels and allow the contents to crystallize so quickly.
Strausbaugh said she had planned to take her grandsons on an upcoming trip to Quincy, Illinois, 90 miles away from Middletown — but is now unsure.
“The longer they put it off, the harder it is for people to be able to leave town and go do anything because Thanksgiving is on Thursday and you’ve got things that you’ve got to prepare for and get ready for,” she said. “So we’ll probably just stay at home, turn our furnace off, and wait till the all clear, and go from there.”
The post Court clears way for Army plan to detonate hazardous chemicals in Iowa appeared first on Washington Post.