Trump’s Stargate AI Project in Huge Trouble As $18 Billion Data Center Shrivels Toward Oblivion

September 25, 2026
in News
Trump’s Stargate AI Project in Huge Trouble As $18 Billion Data Center Shrivels Toward Oblivion

Donald Trump’s $500 billion AI infrastructure project is in major trouble in New Mexico, as a pivotal data center project appears to be shriveling on the vine.

Early on Thursday, the AI company Oracle sent out a notice of “force majeure” to the Blue Owl Capital, the lender backing a massive hyperscale data center critical to the president’s ambitious AI project, Bloomberg reported.

Typically reserved for unexpected catastrophes like the outbreak of war, natural disaster, or massive social upheaval, Oracle invoked force majeure in order to shield itself from financial liability over the project’s failure to secure certain development permits.

Zooming out, the notice is being viewed by financial commentators as an attempt by Oracle to wriggle out of responsibility for upcoming payments in the increasingly likely event that the data center isn’t finished by 2028.

When — or if — the New Mexico facility goes online, the plan was for Oracle to become the primary tenant, making use of the facility’s 2.45 gigawatts of compute power for AI. A part of the $165 billion AI campus called “Project Jupiter,” the data center has run into heaps of local opposition and delays.

Back in May, it was reported that Oracle had cancelled plans to erect a massive natural gas plant needed to power the facility, after developers failed to secure land use permits from both state and federal authorities. Instead, Oracle said it was pivoting to a solution using solid oxide fuel cells (SOFCs), an experimental stopgap that’s never been tried at this scale.

Indeed, the single largest deployment of SOFCs to-date appears to be an 80 megawatt project in South Korea — a drop in the bucket compared to the 2.45 gigawatts required if the data center is to reach its original planned potential.

Oracle is the main infrastructure company behind Trump’s Stargate project, a private build-out involving OpenAI on the software side and the Japanese investment giant SoftBank on the financial management side. Oracle has already struggled mightily this year, with lenders growing jittery about Jupiter’s financial prospects as early as January, forcing the cloud and infrastructure giant to lay off thousands of workers in an emergency cost cutting spree.

Clearly even those drastic maneuvers weren’t enough to right the ship, as Oracle now braces for a serious financial impact.

Keep in mind, the data center in question is just the first piece of the Project Jupiter campus, itself just one component of the $500 billion Stargate. If the ship piloted by these titans of industry is already on the rocks, it doesn’t exactly bode well for the rest of Trump’s megaproject — nevermind the AI buildout writ large.

More on AI: Tech Companies Are Setting Themselves on Fire to Keep Up in the AI Race

The post Trump’s Stargate AI Project in Huge Trouble As $18 Billion Data Center Shrivels Toward Oblivion appeared first on Futurism.

Mortgage rates climb for 5th  week, pushing 30-year home loan above 7%
News

Mortgage rates climb for 5th week, pushing 30-year home loan above 7%

by Los Angeles Times
September 25, 2026

The average long-term U.S. mortgage rate rose this week above 7% for the first time since January 2025, the latest ...

Read more
News

‘Incorrect and extreme’: Colleagues chew out Trump judges over ‘abhorrent’ ICE policy

September 25, 2026
News

The Night Outkast Was Booed at an Award Show Was Also the Night That André 3000 Accurately Predicted Hip-Hop’s Future

September 25, 2026
News

What Jennifer Garner told Ben Affleck about playing his love interest in new film before being recast

September 25, 2026
News

‘The Traitors: New Blood’ Marks NBC’s Top Unscripted Premiere in 6 Years With 6 Million Viewers

September 25, 2026
Cooper Flagg trading card with game-worn debut patch sparks auction frenzy, sells for $8.04 million

Cooper Flagg trading card with game-worn debut patch sparks auction frenzy, sells for $8.04 million

September 25, 2026
Supreme Court hands Trump big win in voter fight: ‘Dangerous decision’

Supreme Court hands Trump big win in voter fight: ‘Dangerous decision’

September 25, 2026
Colossal hurricane explodes back into Cat-5 monster as wind speeds ramp up and it heads toward US

Colossal hurricane explodes back into Cat-5 monster as wind speeds ramp up and it heads toward US

September 25, 2026

DNYUZ © 2026

No Result
View All Result

DNYUZ © 2026